Installation Capacity: 3200cmh TOTAL CAPACITY (CMH) 3200 CAPACITY PER CELL (CMH) 800 NO. OF TOWER 01 NO. OF CELLS
Read More1) Installation Capacity: 9600 cmh TOTAL CAPACITY (CMH) 9600 CAPACITY PER CELL (CMH) 1600 NO. OF TOWER 01 NO. OF CELLS 06
Read MoreInstallation Capacity: 14400 cmh TOTAL CAPACITY (CMH) 14400 CAPACITY PER CELL (CMH) 1600 NO. OF TOWER 01 NO. OF CELLS 09 HOT WATER TEMP (°C)
Read MoreInstallation Capacity: 6400 cmh TOTAL CAPACITY (CMH) 6400 CAPACITY PER CELL (CMH) 1600 NO. OF TOWER 01 NO. OF CELLS 04 HOT WATER TEMP (°C) 34
Read MoreInstallation Capacity: 9600 cmh TOTAL CAPACITY (CMH) 9600 CAPACITY PER CELL (CMH) 1600 NO. OF TOWER 01 NO. OF CELLS 06 HOT WATER TEMP (°C)
Read MoreInstallation Capacity – 4000 cmh TOTAL CAPACITY (CMH) 4000 CAPACITY PER CELL (CMH) 2000 NO. OF TOWER 01 NO. OF CELLS 02 HOT WATER TEMP (°C) 45
Read MoreInstallation Capacity: 14000 cmhTOTAL CAPACITY (CMH)14000CAPACITY PER CELL (CMH)2800NO. OF TOWER01NO. OF CELLS05HOT WATER TEMP (°C)42COLD WATER TEMP (°C)32WET BULB TEMP (°C)28FILLOPTI GRID
Read MoreTOTAL CAPACITY (CMH) 2125 CAPACITY PER CELL (CMH) 425 NO. OF TOWER 02 NO. OF CELLS 05 HOT WATER TEMP (°C) 40 C
Read MoreCAPACITY PER CELL (CMH) 1300 CAPACITY PER CELL (CMH) 650 NO. OF TOWER 02 NO. OF CELLS 01 HOT WATER TEMP (°C) 42 COLD WATER T
Read MorePROJECT Supply and Installation of advanced Trickle Grid Fills for Cooling Tower Performance improvement of CT#3 (6 Cells – 13000 CMH) CHALLENGE & EXECUTION Hindalco RPD was distressed with the poor performance of their exi
Read MoreREVAMPING PROJECT BPCL’s Mumbai RFU has undergone a major revamp in September 2021 to increase the design capacity from 3600 MTPD to 6000 MTPD. On 6th November 2021, RFU started processing 6000 MTPD of feed from CDU 3 stabilized naphtha and CDU4 stabilized naphtha. CHA
Read MorePROJECT Supply and Erection of Wind Wall Partition for Cooling Tower Performance improvement for 44 Cells (11Cells × 4 CT) with Pultruded FRP Structure. EXECUTION Encon supplied FRP Structural material along with wind wall panels and provided Service team f
Read MorePROBLEM STATEMENTTo replace existing Sigma Cooling Tower with Counter flow Pultruded FRP Cooling Tower in existing basin which offers high thermal efficiency and reduce maintenance to reduce the power consumption in Howden and Syn gas compressor.The quintessence of this project is the
Read MorePROBLEM STATEMENT Improve the thermal efficiency improvement of an induced draft cooling tower to reduce cold water temperature for an increase in overall plant production efficiency.Thermal Understanding of Fills The heat transfer rate in a wet cooling tower system is directly dependent